Simonds express Westbury Beckett facade
Your house looks so good ours is still like a bomb went off lol. So much to get sorted!!
Simonds Express Westbury Build
Aircon installed yesterday and this morning. Some teething issues looks like zone controller maybe faulty or something but working just for the whole house for now. Pretty awesome 30 degree…
Simonds Express Westbury Build
I would say do basically every internal wall.
Here is what we did:
Simonds Express Westbury Build
Bradford Soundscreen R2.5.
Keep in mind though if you're serious about soundproofing you will also have to put in heavier doors like it's almost pointless to do the insulation without better…
Simonds Express Westbury Build
These came yesterday!!
Also been sealing the grout the last 2 nights... This is about the worst job lol. Stupid roller bottle garbage thing takes so long.
Simonds express Westbury Beckett facade
Corners of the windows/doors and in the corners of the rooms. As the house settles this is where there'll be cracks - they just need to putty them up and…
Simonds Express Westbury Build
Keys Thursday! Surprised the wife and took her there.
Now all the fun starts!!
Simonds Express Westbury Build
Valuation is tomorrow - should be straight forward so should just be next day or two and we'll finally have keys!!
Just a quick update - pulled all the network cables…
Simonds Express Westbury Build
Didn't end up getting keys and still not sure when. Going to give bank a call tomorrow and get a definite date for their valuation as we've given where we…
Simonds Express Westbury Build
Occupancy Permit received today! Just waiting on bank now.
Simonds Express Westbury Build
Garage door last week finally came. House is all clean inside even the oven is in. Just waiting on final walk through and bank. Fingers crossed.
Simonds express Westbury Beckett facade
One thing I hate that I'd change and never thought of - speaking of gaps.
The bathroom vanity - there's this little gap between the bath and it! Too small to…
Simonds Express Westbury Build
Snuck past today.
Oven in. Downpipes painted. Flyscreens on.
Just waiting on garage door.
Also have organised Aircon and solar installs. Ended up going with ActronAir ESP Plus Platinum 17kw system (ERV3-17AS /…
Simonds express Westbury Beckett facade
Damn wishing we'd got the extra laundry bench space!!
Simonds express Westbury Beckett facade
They gave us the guys number who was doing the driveway - $1200 cash job boo hoo there is a bit of work involved with getting rid of the guttering....…
Simonds Express Westbury Build
Driveway the other day. Tiler back today and finished splashbacks and looks like painter been back in to touch up around the place.
Also carpet done!
Just waiting on that garage door..
Simonds Express Westbury Build
Crazy how fast things are moving now!
Electrical fitout done today. Most of data and speaker cabling points done waiting on garage door to do termination in garage.
Hot water connected, shelves…
Simonds Express Westbury Build
More updates.
Tiles still in progress, all going well. Were meant to finish today but I guess back tomorrow! Grouting meant to be finished tomorrow as well. Plumbers back on Thursday…
Simonds Express Westbury Build
We're very suited to the Express build I think - like we just wanted "a house" not fussed about anything with it really.
I do like the tiles and like…
Simonds Express Westbury Build
It was approx. $4500 extra. We did push for and got a credit back for the carpet of approx. $1300. The credit for carpet wasn't on original contract so be…
Simonds Express Westbury Build
Few things happening!
*Bricks been cleaned
*We have downpipes
*Tiling starting
*Joinery complete just waiting on Kitchen benchtops (Ceaserstone).
Gotta work out if we want to widen the driveway. Also a good addition found to…
Simonds Express Westbury Build
Really hoping before xmas but still probably mid Jan. Supervisor is doing a really good job to get us there hopefully! It seems like its going so quick could expect…
Simonds Express Westbury Build
From today. Render done, paint done, joinery started and dirt been filled in mostly. Awesome!
Simonds Express Westbury Build
Bricks finally finished last week! Plasterer did touch ups and painters been in this week as well, joinery started today hpoefully.
Even got some mowing and tidy up done on the…
Simonds Express Westbury Build
Yep Blackwood and we went tiles in lounge & family rooms with dark (not quite black) grout after reading other posts here.
Did you talk to site supervisor or the tradies?…
Simonds express Westbury Beckett facade
Our MySimonds showed 23rd December as well, has bumped to 28th but site supervisor has told us realistically couple of weeks into Jan.
Simonds Express Westbury Build
Bricks completed, electrician been back in to cut their holes and I have got the data points holes cut at same time, windows covered over inside for painting and plasterer…
Simonds Express Westbury Build
Finally some updates!
Bricks still going, not too fussed though as a really great job.
Plastering done and just about ready to move onto fixings. Electrician back this week.
Simonds Express Westbury Build
It's ambiguous or depends who you ask. My understanding is if it touches the telecommunication network then yes you would need a cabling license or signed off by someone with…