HIA Contract - Contract Period Start Date? Help!
We have a contract period of 30 weeks to build our home. I was wanting to know when the 'contract period' commences?
The building started on May 5th this year,…
60mm Overhang On Bricks?
The site supervisor has said that the are going to drill into the existing slab and add another slab underneath it and give us an extension onto our patio (because…
60mm Overhang On Bricks?
We have just been down to see our house and we have noticed that around the study area there is a 60mm overhang on the bricks over the edge of…
Just Poured H Class Slab Cracks?
They wouldnt stop. They have already put up the frame, but even the builders were saying hey should we be doing this with these cracks? But they got the…
Just Poured H Class Slab Cracks?
Since i last posted the cracks have gotten a lot worse. The main supervisor has said he cant get a structural engineer to look at it for 3 weeks…
Late Payments?
So it would be about $24 a day? I thought it was 24% on each payment! I was freaking out. We werent aware it was per annum.
Late Payments?
We are building with ProCorp and our interest on late payments is 24%. We have to pay within 5 working days as stated in the HIA contract. I…
Just Poured H Class Slab Cracks?
Im not sure but they put down styrofoam waffle looking things..
Just Poured H Class Slab Cracks?
No they didnt, it has just been left uncovered. I know you can get cracks from the shrinkage of the concrete when it dries.. we just didnt expect so…
Just Poured H Class Slab Cracks?
We have just had our H Class slab poured last Thursday and today when we went to our block we have noticed all these cracks through the slab. My…
Just Poured H Class Slab Cracks?
We have just had our H Class slab poured last Thursday and today when we went to our block we have noticed all these cracks through the slab. My…