My build is coming along really well! Since my last post the following has been done.
Frame completed
Windows installed
Sarking done
Plumbing rough in
Gutter and fascia installed
Roof completed
Bricks delivered
Here is a few photos…
Rawson Seaview 36: Practical Completion Date - 11/3/16 (Syd)
Quick update on the build... Our builder was busy last week getting the site ready for slab pouring. All the form work, plumbing etc has been done and slab was…
Building with Adenbrook Homes {sydney}
Hi SychoAngel, just found your thread from searching 'auburn'.
I'm going private builder, and I will be submitting the plans to auburn council this week.
What are the delays you're…
Who is building with Beechwood
OUR HOUSE TIMELINE FOR ANYONE INTERESTED. CENTRAL COAST AREA.
Land purchased 12/4/13
Deposit paid 3/7/13
Contracts signed 21/11/13
Bank letter received 16/1/14
28 day letter issued 17/1/14
End of 28 days 13/2/14
Pegs 14/2/14
Fill spread 25/2/14
Site fence 7/3/14
Piers 13/3/14
Pre slab work 21/3/14
Slab 27/3/14
Frames/Trusses delivered 31/3/14
Frame 3/4/14
Trusses/windows 10/4/14
Roof 2/5/14
Brickwork started 9/5/14
Brickwork finished 28/5/14
Electrical/plumbing…
Who is building with Beechwood
Thanks merlotguest I'll post some as soon as possible. Our build has gone really great our ss was great he has addressed everything I have brought up to him and…
Who is building with Beechwood
Oh you poor bugger! I would be a mess!!
Just think this time next week you will be all unpacked and living in your beautiful house
Who is building with Beechwood
Hap hap happy here.
Popped out to see the house and gyprock has been completed. And my kitchen was almost done.
Sorry for the flood…
Who is building with Beechwood
Hi all. Haven't posted in a little while
We now have slab, frame & windows and glass doors. (And a pile of sand - perhaps a sign of bricks to…
Who is building with Beechwood
how long did it take you from gyprock to painting?
About 4 weeks it was finished on 24/7 then you have architraves, skirting, doors, kitchen cabinet install, vanity install, shelving,…
Who is building with Beechwood
Framework and windows turned up today hopefully the rain stays away long enough for them to go up!
Who is building with Beechwood
We have had a pretty good week thanks to my amazing ss! The lighting is getting fixed. A new window has been ordered and my gyprock was delivered today ready…
Who is building with Beechwood
We have now settled on our land!!! Woohoo!! Off to council we go, FINALLY!
Who is building with Beechwood
So I thought I would upload some pics of where we are up to with the pool build. Next step is the coping, waterline tiles and stackstone on the water…
Who is building with Beechwood
haha im on the block website now checking them out!
We also chose the same tiles as Karstan and Max's bathroom from this season but in Matt (they have gloss) hehe....…
Who is building with Beechwood
Thanks natlyn!! I LOVE them so much pics don't do them justice. They are the tiles that Kyal and Kara used in the bathroom for the feature wall on…
Who is building with Beechwood
we're way off starting our build...but at least something is happening on our land...we have our street started
Also can someone please remind who…
Who is building with Beechwood
Elblow they are mild steel. Pgh brick.
Who is building with Beechwood
Hi guys
How is everything going?
My bricks and roof are finished and we had the brick clean today. Due for electrical tomorrow and gyprock monday. Had a call…
Who is building with Beechwood
BW have there own insurance. You should get a copy of it at your contract signing. : )
Who is building with Beechwood
hi all its good to see everyones progress and I'm happy to say today the 9th day our block was benched and we are expecting piering tomorrow