Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Wow Steph!! Your house looks amazing!! [/quote
Thanks so much!!
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
WE HAVE A HOUSE!!! sorry for the delay, we have been super busy and I have been finding it easier to update everything on instagram
We had handover on…
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Aw thanks so much! Need to save some money to get the furniture I want 🤦🏼‍♀️ we have the basics though
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Handover tomorrow, still doesn’t feel real and so much to do
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Yes exactly the same thing happened to us 🤦🏼‍♀️
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
We had PCI last Thursday! There was heaps of paint issues, rangehood isn’t installed, ensuite mirror isn’t installed, some cracked tiles etc but overall alright.
Moving in on Saturday with handover…
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Thank you nope it was $45 all up to upgrade from the laminate we already had included we went with Coral elegance inclusions though which has more of…
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
PCI NEXT FRIDAY, 25 MAY 2018
Coral Homes Noosa 23 - Ormeau Hills: Life after handover
Did you guys pay your final account by cheque on handover day or before straight into there account?
Coral Homes Noosa 23 - Ormeau Hills: Life after handover
Looking good!!! Any photos of the inside?
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
IN LOVE WITH OUR KITCHEN NOW THAT THE VINYL IS INSTALLED
Vinyl is Wood Effects range from Carpet Call in Blonde Wood.
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Heyyy! Our island is 2.63m long and 1m deep. Our pendants are quite big and 35cm in diameter we actually drew it all up on paper from the top…
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Aw thanks so much!!!
The LED strip is still pending.. they haven’t sorted the recess in the overhead cupboards yet. I did talk to the electrician about running it the whole…
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Haha thank you!!! Eeeek, the styling is stressing me out, who knew it would be so hard to choose furniture 🤦🏼‍♀️
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
4 weeeeks! That’s ages
Would love to see
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Thank you, I just wish time would hurry up these last weeks have been so slow!
Coral Homes general build thread
Looks like Informed, which is what we got
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Week 19 starts tomorrow! Sorry have been so slack at updating my forum.. I have started using Instagram to document everything that’s been happening instead for anyone interested it’s:
@CoastalResidence…
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Now in week 18! I am hating this whole being locked out thing! Our flooring is booked for Friday and carpets soon to follow.. PCI date is estimated at 29th…
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Good luck, we went so far over budget even with extensive research 🤦🏼‍♀️
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Glad I could help I had so many issues finding pricing when we started. Our cornerless stacker door fly screens were around $850 - however the did stuff up…
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Thanks guys can’t wait for it to be over! Finding it so hard to find furniture etc...
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Tiling finished this week and painters have started!
Fitout will start late next week and we are expected to have PCI at end of May
Our overhang on our caesarstone bench…
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
I’m glad it’s long but still only 7cm deep some of my products are wider than that!
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
I can’t believe you haven’t seen yours yet! You are basically done I have still been checking in on your build.. I can’t believe you are still have issues…
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Still soooo slow
Render has been done but not painted at the front, bag and paint has been done to rest of house, tiles have started (1 week later and…
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
I have had no motivation to post about the house because it feels like we are moving so slowly in comparison to everyone else 🤦🏼‍♀️
We will be in week 14…
Coral Homes general build thread
Haha I feel you, I am so over my build and nothing happening I never come on here unless it’s to complain or get information whoops