Construction period and liquidated damage in HIA Contract
Hi Experts,
I have received the contract for building a double-storey home with JG King. In my contract, they are showing
Total construction period as 425 days (303 days for construction…
Building 2 storey house with JG KING steel ATLAS 2
Is it all about communication and delay? No issues with built quality?
New house glenfern bricks
Hi Cheema, which colors you went for for upstairs and which bricks in ground floor?
Skirting boards when flooring after handover
Are you advising to get the skirting installed by builder? Or take them uninstalled and install later after flooring?
Skirting boards when flooring after handover
Hi Experienced buddies,
I'm in a situation unable to decide what to do with skirting as doing flooring after handover.
Mine will be double storey with ground floor tiling and first floor…
Fencing transperacy
Hi,
Can someone please help me understanding what how to calculate if my proposed fencing is 30% transparent?
For example for a fence with 1.5m post. 30% of 1.5m is 450mm. Does…
Ceiling cornice
Thanks Bebbsy, appreciate your advice. Will definitely help me deciding.
Ceiling cornice
Please advise which cornice to go with? 75mm or 55mm or upgrade to 90mm or square set?
Ceiling Cornice
Please advise which cornice to go with? Classic look knauf 75mm or 55mm or upgrade to 90mm for $1000 or upgrade to square set for $5200? Building double storey with…
Moving a crossover in Melbourne's west
Hi,
I've deposited for land which will get titled next year June 2018. Due to a rear crossover in corner plot Simonds, Carlislehomes and Metricon confirmed they don't have any design…