Rossmoyne WA - First Build With Ventura
Very well I feel. Upstairs has windows and plaster done, and they will work on the downstairs soon.
Rossmoyne WA - First Build With Ventura
Plaster and windows installed upstairs.
Rossmoyne WA - First Build With Ventura
Grey render coat applied upstairs and ceiling and cornices installed.
Rossmoyne WA - First Build With Ventura
The conduits with 2 wall face plates was $88 for each one. It will be hard to have your own electrician doing it as the builder doesn't allow anyone else…
Rossmoyne WA - First Build With Ventura
I think they are chased into the wall with the electrical cable. I only added the conduits for the tv areas so I can hide cables later on.
Rossmoyne WA - First Build With Ventura
Electrical and air con ducting installed
Rossmoyne WA - First Build With Ventura
Colourbond roof and gutters installed
Rossmoyne WA - First Build With Ventura
Top floor roof framing done
Manhole
Rossmoyne WA - First Build With Ventura
2nd story nearly completed. Just missing the front rooms.
Master Bedroom
Ensuite
Walk In Robe
Rossmoyne WA - First Build With Ventura
1t floor slab down
Concrete stairs
Storage room under stairs
Rossmoyne WA - First Build With Ventura
Brickwork cut ready for stairs to be made
Floortech system
Rossmoyne WA - First Build With Ventura
Scaffolding is up ready to start the 2nd floor.
Rossmoyne WA - First Build With Ventura
Hi Hoothouse,
If you already have a clear idea of what your floorplan looks like, you can just go to these project builders and then pretty much dictate to them what…
Rossmoyne WA - First Build With Ventura
Hi,
No we did not pay extra for a custom design over an existing floorplan. As the salesperson put it, its all about the materials in the end. It doesn't…
Rossmoyne WA - First Build With Ventura
Brickwork (3rd Week)
The 1st floor is pretty much done. Just have a bit of the garage left to do.
Front entrance
Guest bedroom
Stairs location
Laundry
Dining/Living Room
Kitchen/Scullery
Rossmoyne WA - First Build With Ventura
Bricks Delivered
Brickwork (1st Week)
Really happy with the brickwork quality so far. As the next door neighbour is also currently building, we can compare the quality of our brickwork and it…
Rossmoyne WA - First Build With Ventura
Floorplan (Ground Floor)
Floorplan (1st Floor)
Front Elevation
Rossmoyne WA - First Build With Ventura
Hi All,
We have received a lot of valuable information from browsing this forum which led us to decide to build so we would like to contribute our building experience so…