Anyone building in woodlea/rockbank? Why is it so exspensive
Woodlea has much better masterplan compared to other estates in Fraser Rise and Deanside. I live in Fraser Rise and going to build in Woodlea that is why I can…
Building new home - Henley Monaco Nouveau Q1 in Plumpton
We din't get a chance to take any pictures y'day as we wanted to get the inspection done ASAP. Also the flooring is not done yet. but I will upload…
Building new home - Henley Monaco Nouveau Q1 in Plumpton
woohooo.. finally we had our final inspection and looks like we will get our keys by end of month.
That gives me just 7 days to vacate my current house which…
henley Emperor nouveau Q1 at the point plumpton
For us slab was done in the end of July - it felt like eternity to get it going with all the troubles we had with bank, but after that…
henley Emperor nouveau Q1 at the point plumpton
Great... things are moving for you... for us its about to complete now. Had our first of post complete inspection and apart from few paint marks and few spots to…
henley Emperor nouveau Q1 at the point plumpton
That is great, hope your build starts very soon as well.
henley Emperor nouveau Q1 at the point plumpton
Hi guys,
good to see people in this forum who are building in plumpton area. We are building in Orbis green estate.
Our Build - Henley Monaco Nouveau Q1 in Melbourne West
that is really strange mtz.. for us its kind of always open.. also they did not put fence on one side so if we can't go through front we can…
Building new home - Henley Monaco Nouveau Q1 in Plumpton
Checked today - plaster boards are up -half the brick work is done and it looks like home now
Our Build - Henley Monaco Nouveau Q1 in Melbourne West
we have similar situation mtz with slab feels very high - but when the start doing the brick work you completely forget that slab was so high
Building new home - Henley Monaco Nouveau Q1 in Plumpton
Update - Roofing is nearly done - solar hot water panels are being installed this week. Also bricks have arrived and as per admin email they are scheduled to…
Our Build - Henley Monaco Nouveau Q1 in Melbourne West
Great news mtz... now you will get that urge to go on to the site and check the daily progress
Building new home - Henley Monaco Nouveau Q1 in Plumpton
Slab is done.. and they have straight away started on framing. Slab was done on tuesday and today when I drove past they had half the frame up already...
Building new home - Henley Monaco Nouveau Q1 in Plumpton
Update:
Slab going in today. Before going to office went to site to have a look and concreters were on site. Hopefully rain stays away today.
Building new home - Henley Monaco Nouveau Q1 in Plumpton
Still no update from the site. Spoke to admin and she advised that concreter was suppose to be come this week and framing for next week - but due to…
Building new home - Henley Monaco Nouveau Q1 in Plumpton
Update for the week:
Looks all good for slab next week. They have pretty much done pipeline and according to Henley's admin email "concreters are hoping to commence mid to late…
Building new home - Henley Monaco Nouveau Q1 in Plumpton
We are building a new house with Henley - Monaco Nouveau Q1 in Plumpton - Orbis estate.
After a long long delay due to Bank taking its own sweet time to…
Our Build - Henley Monaco Nouveau Q1 in Melbourne West
Hi mtz08,
I haven't yet created a blog.. will do so this week and let you all know
1st time building - which house are you building in the Point estate ?
Our Build - Henley Monaco Nouveau Q1 in Melbourne West
We are building in Plumpton (Caroline Springs) Orbis estate
Our Build - Henley Monaco Nouveau Q1 in Melbourne West
Finally some good news - saw temp fencing and portaloo on land... after long long wait construction is finally starting
Building henley Monaco Nouveau Q1 - Our thread :)
They started cutting our site Friday... Check out the background. Think we'll be using every cent of our rock removal allowance !!
Goodness me....…
Building henley Monaco Nouveau Q1 - Our thread :)
Your build is really flying sunct. This gives me some comfort that we will be able to settle in before summer. Finally received the building permit on friday (6 weeks…
Building henley Monaco Nouveau Q1 - Our thread :)
Congratulations Cpl on keys... now time to set up all the toys.
Mtz08 we asked for stepdown garage and they are charging us $450 for that.
Our Build - Henley Monaco Nouveau Q1 in Melbourne West
I also thought so, but only they know why is it taking so long. Only two houses have started in estate and both seems to be house and land package…
Our Build - Henley Monaco Nouveau Q1 in Melbourne West
That's great Aston Boy. Our land was titled on 22nd Apr and we are still waiting for building permit. Melton council is taking forever for approval
Our Build - Henley Monaco Nouveau Q1 in Melbourne West
That really hurts - to have such last moment changes.
Initially you think just get to the land settlement and then it will fly - but the real trouble only…
Our Build - Henley Monaco Nouveau Q1 in Melbourne West
For us footing cost is only 7.5K - but then they also had to change slab from M to H2 - so that added 5k + Cut and fill…
Our Build - Henley Monaco Nouveau Q1 in Melbourne West
Congrats mtz08 and cpl.
Well for us we are still waiting for the building permit - Melton council is taking forever.
Land settlement happened on 22nd of May - and permit applied…
Our Build - Henley Monaco Nouveau Q1 in Melbourne West
Hi guys,
its great to follow everyone's progress so far. We are also building Monaco Nouveau Q1 in Plumpton (Orbis Green estate). Land is settled just this week so we have…