Burbank Custom DS- 4 months post Handover !
Hello hello All
I thought I check- in today to see how everyone else builds or peoples been…
Your experience with Burbank
From reading other Burbanks build from SLAB its:
Single storey - approx around 15-20 weeks (4-5 months)
Double storey - 35-40 weeks (7 -8 months)
Hi Deepmon
Congrats on signing with burbank
An…
Your experience with Burbank
Hi Shamon
Congrats exciting time ahead
Has your build gone to site yet ? Are you building single or double ? When it does you…
Burbank Custom DS- 4 months post Handover !
Hiya Sofia14
Sorry for the late reply been busy with the move and unpacking
Yes we have wall faced toilet suite I dont know…
Dee & Dan's First Home Build -HGWA- CURTAINS ARE IN!!!
Oh exciting time ahead dee .. Not long to you can put all these lovely furniture in ..
We also couldn't decide and bought 2 of each ( black &…
Dee & Dan's First Home Build -HGWA- CURTAINS ARE IN!!!
Love your splash back DEE .. Specially the laundry one...
Your home looks near complete , how long to go ?
Burbank Custom DS- 4 months post Handover !
Week 36 - Handover / We Got Keys
Mon 08 Sep - Sun 14 Sep 2014 (Day 183-187)
Final Inspection was booked in for Thursday @ 9:30 am this week, all…
Burbank Custom DS- 4 months post Handover !
Hi All,
We started the process searching for our block in April 2013 and had Settlement of our block in the Cairnlea Estate on 26th June 2013...it has been a…
Burbank Custom DS- 4 months post Handover !
Week 35 - PCI Done, Settlement BOOKED
Mon 01 Sep - Sun 07 Sep 2014 (Day 178-182)
Just a quick update to let you know PCI was done today. No major issue…
Double Story Build - Photos and an Update
I totally agree with nnsha1 .. Don't see any probs with your paint colour ( must admit its a little hard as the colour samples are just on small paper)…
Burbank Custom DS- 4 months post Handover !
Week 34 - Independent (PCI) Inspection & Occupancy Permit
Mon 25 Aug - Sun 29 Aug 2014 (Day 173-177)
Just a quick update to let you know how this weeks been
-…
Burbank Custom DS- 4 months post Handover !
Hey anocha, I was also looking at your pix and thought the same.. no mine is just the standard Austral (Chestnut) Was yours an upgrade?
By the way think we have…
Burbank Custom DS- 4 months post Handover !
Thank you all for dropping by my thread and well wishes... Dsbuild is correct in me feeling excited yet same time nervous as I am at the moment thinking what…
Burbank Home in Eynesbury
Great so just monior issues is that why handover is only 1 week apart ?Did you have a independent inspector in sight ?
Also have you received occupancy permit ?
Burbank Custom DS- 4 months post Handover !
Week 33 - Outstanding Issue fixed/PCI Booked
Mon 18 Aug - Sun 24 Aug 2014 (Day 168-172)
After (3) weeks of no activities we finally have some update to post…