Builder not providing dates
Yep, Im a software developer, so I understand your frustration but we can control our env more than they can. Unfortunately you are just going to have to wait. Even…
Builder not providing dates
They aren’t going to know this far out. You only have to have someone/something not available and that can throw the schedule. I know it’s frustrating but you probably won’t…
Site supervisor meeting
I would say try and set some expectations for example. We told out site supervisor that we wanted an update every second Friday. We would call or text at the…
Fibreglass Pool
I would question what sort of neighbour would assume it’s ok not to ask. Unless it’s an empty block of land then that might be different.
A friend had their front…
Builder Incentive how does it work?
I’d love to know how many people qualify for the discount
Builder Incentive how does it work?
I don’t think this is how most builders do it. They have a package and it covers a bunch of things it’s added onto the price and that’s the price.…
Wide block with narrow floorplan
There are a few things you can do.
1. Most builders have no problem with you extending rooms, you could simple take each room out wider.
2. Position it on one…
Got the keys today
We are loving it. The kids use the bath a couple of times a week.
They are a central coast builder, when we started the process the had a rule that…
Interim Occupational Certificate change coming
We’ve had the keys since mid May and we haven’t yet got the drive way sorted. So yes it will cause all sorts of issues if they don’t modify what…
Bath moved! Value of private inspection?
We had a private inspection done prehandover it was absolutely worth it. They found things we didn’t know to look for. That said we had no major issues.
Interim occupational certificate
It’s full of water but not the type you want to swim in. We’ve moved in and we are currently getting quotes for some hard landscaping that needs to be…
Interim Occupational Certificate change coming
My understanding is that you can no longer get an interim certificate you can only get the full certificate, so things like driveways will need to be completed before you…
Building on a sloping block
You can get rainwater tank flower beds that double as retaining walls. These might come in handy for what you need and may reduce the cost.
Your images aren’t showing
KDR - Rawson Chifley 42 mark ii in Newcastle.
Wow. It’s really coming along. I love your kitchen selections.
Got the keys today
Yes we put one both bathrooms. They are great just make sure you label the switches so the kids don’t leave them on
Fixing Stage and electrical
Depends what your contract says. Who is your builder? Generally if you have a progress payment say for the electrical stage 90% could be completed for them to ask for…
Rawson Homes - General Thread
Get a copy of their contract before you send any money with them. Make sure you are happy with it before moving forward.
Got the keys today
Yes we did we took our Wishlist and sat down with there draftsman and started from scratch. we had all the contour surveys done and existing block diagrams to show…