The CARLISLE HOMES & SPECTRA General Information Thread
Hi Nadhi,
Yes we did. He just picked up some little pieces of defects. He said there are no major issues but we spot other defects which he did not pick…
The CARLISLE HOMES & SPECTRA General Information Thread
Hi Guys,
Do you know how long it takes from PCI to handover? We have done our PCI last Tuesday but after that we cannot get in touch with our SS.…
The CARLISLE HOMES & SPECTRA General Information Thread
Hi melbfhb,
How do we know if the rangehood is not ducted to outside? just checking if there are some kind of grilles on the brick wall outside? Sorry it sounds…
The CARLISLE HOMES & SPECTRA General Information Thread
Hi guys,
Can anyone recommend a good exposed aggregate concrete driveway company in Southeast Melbourne area? Thanks.
The CARLISLE HOMES & SPECTRA General Information Thread
Hi All,
We just got a PCI date. Any tips on PCI and handover? Does anyone know how long it takes from PCI to handover? Thanks.
The CARLISLE HOMES & SPECTRA General Information Thread
Hi to those using private inspectors,
Do your inspectors help you to negotiate or push CH to rectify defects when CH don't want to rectify some of the defects? Thanks.
The CARLISLE HOMES & SPECTRA General Information Thread
Hi, You just need to let you sales and CLE know as soon as possible. We changed our house design one month after we paid the deposit. Our sales didn't…
The CARLISLE HOMES & SPECTRA General Information Thread
Hi All,
We paid upgrade for providing Laminex Riven laminate in lieu of standard laminate to Kitchen overhead cupboards. Does anyone have done the same and know if the bottom panel…
The CARLISLE HOMES & SPECTRA General Information Thread
Hi, We are building a double storey house. Our frame inspection was done 2.5 weeks after our slab was poured.
You have to ask your site supervisor about the expected…
The CARLISLE HOMES & SPECTRA General Information Thread
We have used NHI for three inspections now and we are quite happy with them so far. Before we started we were hesitating between the two companies as well but…
The CARLISLE HOMES & SPECTRA General Information Thread
Congratulations on signing your contract! 8 weeks for us between signing contract and site start including Xmas closing down period in the middle.
The CARLISLE HOMES & SPECTRA General Information Thread
Thanks @ubet7 and @Orangebottles, I checked our contract and unfortunately it says 7 days not 14 days. We can hold back the payment for a couples of days and that's…
The CARLISLE HOMES & SPECTRA General Information Thread
Hi All,
We just received an invoice from CH although we haven’t done our inspection of the construction stage yet because our site manager said he is fully booked and couldn’t…
The CARLISLE HOMES & SPECTRA General Information Thread
Yes, it will be fine. We just needed to gave our broker's email and phone number to our CLE. We signed our contract in the morning and our CLE emailed…
The CARLISLE HOMES & SPECTRA General Information Thread
Hi All,
Did anyone already build with square set cornice? How was the craftsmanship? Was the ceiling leveling ok? Cheers
The CARLISLE HOMES & SPECTRA General Information Thread
Hi ericaust23,
Thanks. I got the same answer from our CLE as well. It is quite disappointing. Good luck with your built.
Cheers
Lily
The CARLISLE HOMES & SPECTRA General Information Thread
Hi kd_w22,
Thanks for your suggestion and sharing your experience. I am a bit disappointed with CH about this marketing 'attraction'. I am feeling we have to have our own inspector…
The CARLISLE HOMES & SPECTRA General Information Thread
CH offers independent inspection control throughout the construction. Does anyone know if we as owners would get any information or communication about the 3rd party inspection they have done during…
The CARLISLE HOMES & SPECTRA General Information Thread
Hi VMEM,
We also upgraded all the glass in our house to double glazing. Our house is still under construction so I can't feel the difference yet but I think the…
The CARLISLE HOMES & SPECTRA General Information Thread
Hi Mrs Summer,
Congrats! Our slab was poured yesterday and framing is to be completed in two weeks. so exciting!
The CARLISLE HOMES & SPECTRA General Information Thread
Hi, we received our final drawings one week before our site start.
The CARLISLE HOMES & SPECTRA General Information Thread
We got the upgrade request of MCP10/F5 timber frame rejected too. They just said they don't do it.
Lily
The CARLISLE HOMES & SPECTRA General Information Thread
Hi Pearz,
We asked Carlisle this at our Tender and Contract. They just told us they cannot do it but couldn't or didn't want to explain why they cannot do it.…
The CARLISLE HOMES & SPECTRA General Information Thread
Hi Orangebottles,
Thanks. You are so lucky to live next door of your new built. We have to drive a long way to see our site. We just saw more and…
The CARLISLE HOMES & SPECTRA General Information Thread
We are hesitating to choose between Darbecca and New Home Inspections as independent building inspector. Does anyone have experience with them and would like to share your thought? We will…
The CARLISLE HOMES & SPECTRA General Information Thread
Thanks. I saw their name on the forum as well. We will check it out. cheers
The CARLISLE HOMES & SPECTRA General Information Thread
Hi Everyone,
We start looking into hiring a private building inspector. Just wondering if anyone can give some recommendation on which phase we should hire an inspector to get the best…
The CARLISLE HOMES & SPECTRA General Information Thread
Hi There,
We are the same as well. We have to pay the Asset Protection directly to our local council. We didn’t know this until our tender appointment. When we questioned…