Thomas Archer Hue 44 Bayside Build - 2021

Yes. 1% if site start is 10-12 months from time PSQ is signed, 2% if 13-15 months and if 16+ months then they should be providing you with a new…

3 years3 yearsmaverick123maverick123 posted:
Thomas Archer Hue 44 Bayside Build - 2021

Shouldn't the price only really change if the site costs are greater than what was allowed for in your PSQ and/or if you make any upgrades as part of your…

3 years3 yearsmaverick123maverick123 posted:
Thomas Archer Hue 44 Bayside Build - 2021

Have you had your pretender yet? Ours is meant to be next month so hopefully we meet that date.

3 years3 yearsmaverick123maverick123 posted:
Thomas Archer Hue 44 Bayside Build - 2021

Did TA give you a build month when you initially paid your deposit?

  ⋅  1
3 years3 yearsmaverick123maverick123 posted:
Thomas Archer Nouveau 41 Glen Eira Build [2021]

Has your build started yet?

3 years3 yearsmaverick123maverick123 posted:
Thomas Archer Hue 44 Bayside Build - 2021

Have you received your pre-tender yet? If yes, was it far off your PSQ?

3 years3 yearsmaverick123maverick123 posted:
Thomas Archer Evoke (Modified) Kingston Build - 2020/2021/20

How is your build progressing?

3 years3 yearsmaverick123maverick123 posted:
Thomas Archer Nouveau 41 Glen Eira Build [2021]

Do you know what maximum % of the house the ActronAir Platinum Que 21KW unit heats and cools at the same time?

3 years3 yearsmaverick123maverick123 posted:
Thomas Archer Hive 45 - Boroondara [2021]

Our PSQ included the number of steps in the split slab that had been allowed for.

3 years3 yearsmaverick123maverick123 posted:
Thomas Archer Hive 45 - Boroondara [2021]

Do you know how many steps you need to meet the 400mm step down in the slab?

3 years3 yearsmaverick123maverick123 posted:
Thomas Archer Hive 45 - Boroondara [2021]

We are at a similar stage to you!
What joinery list did you receive from them?
With the 1.5m fall, how many steps have they allowed for across your slab?
Also keen to…

Joined homeone
28 August 2020

Australia's largest home building and renovation
community with over 1.8 million posts

Home
Pros
Forum
Start a new topic
About
Advertise
Contact Homeone
Articles
All comments made express the views and opinions of the author and not the Administrators, Support nor Homeone Australia & New Zealand
© Homeone Australia & New Zealand All Rights Reserved ‎2001 - 2024

Australia's largest home building and
renovation community
Homeone
About

Terms
Privacy

Follow homeone on FacebookFollow homeone on Twitter
All comments made express the views and opinions of the author and not the Administrators, Support nor Homeone Australia & New Zealand
© Homeone Australia & New Zealand All Rights Reserved ‎2001 - 2024