Please ignore the battern lights as they will all be replaced with downlights post handover. It was much cheaper to do it this way.
Please ignore the battern lights as they will all be replaced with downlights post handover. It was much cheaper to do it this way.
Building Emperor 48
HI JustMia,
You're right about the handles Darker Tiles will look great. Are you doing floor to ceiling?
I don't have a photo of the WIR in…
Building Emperor 48
Hi JustMia,
i believe house will be finished by mid November. there is not much to do really. just fixing up some stuff. complete the garage and the rendering.
I'm glad you…
Building Emperor 48
HI all,
Uploading a couple of photos now that the scaffolding has been removed.
Building Emperor 48
HI Emperor41,
The colour is Shale Grey. I originally went with Surfmist but it got denied by the developers when it got sent for approval.
In their Estate Guidelines they had all…
Building Emperor 48
Hi Everyone,
Some more photos of the build. It is progressing very well. Few issues that i need to bring up with our new supervisor.
Overall they have done a great job…
Building Emperor 48
Hi Ash,
Thank you and Sorry for the delayed reply, We chose the following :
You should be able to chose what you want when you go for Colour selection and you…
Building Mainvue Aegean430 - 45sq in Berwick Waters
Wow that's a good price considering today's prices. when did you secure the block? I'm sure the price has gone up 100k already.
In terms of framing, the longer they take…
Building Mainvue Aegean430 - 45sq in Berwick Waters
How much did land cost you in Berwick Waters? and what size is your block?
Building Mainvue Aegean430 - 45sq in Berwick Waters
Congrats Aegean430. Without realising you will be at lock up stage. I have to say they do progress very quickly unlike the admin process which is very slow.
Building Emperor 48
Thank you Aegean430,
Wishing you all the best for our build. Let's hope they don't do a reverse build on yours due to Brick layer shortage.
I'm not a big fan of…
Building Emperor 48
Thank you Aegean45,
The colour is Urban and it is a Cat1 , I originally wanted to put the statuario maximus but it was a expensive so…
Building Emperor 48
Hi,
Yesterday we paid a visit to our site and the Stone benches have been installed. I cannot wait for the external works to be completed.
THere's still quite a few things…
Building Mainvue Aegean430 - 45sq in Berwick Waters
Congrats Aegean430. Can't wait to see it come together.
Building Emperor 48
Hi All,
Just posting some photos of the progression so far. Tiling in all bathrooms + Powder rooms almost completed.
Building Emperor 48
HI all,
Apologies for being slack, a fair few things have been done to the house since. The bricking stage is finished. just waiting on Cladding.
The real surprise is the inside.…
Building Emperor 48
hmm, i did the reverse of what you have done in terms of ceiling. Upgraded the ceiling downstairs to 2700 and left the upstairs standard.
I can tell you now that…
Building Emperor 48
70mm Island bench from memory was about 3k. i did not upgrade the Carpet through Henley, what i did do though is get the best underlay - 10 mm underlay,…
Building Emperor 48
Hi ,
The bricks I selected are Austral Access Ash - Category 3, there were some really nice ones in Category 3. It depends if you like Dark or light. I…
Building Emperor 48
They have started bricking. I hope it will be finished by then of this coming week.
They have also finished plastering the house, They are doing a reverse build on mine.…
Building Emperor 48
Hi Everyone,
Looks like they will start the brickwork very soon. I had an issue there the Gas point that was meant to go in the Alfresco area but somehow between…
Building Emperor 48
We chose the glass ballustrades with the timber staircase. Cost was just under 5k for the glass balustrade.
I hope it will be ready by Christmas. It sure does look like…
Unhappy... should we start again and find another builder or
I went through the same dramas as you at the beginning. I originally put a deposit down with the big M, They lured me to put down a deposit as…
Building Emperor 48
Hi ,
It is indeed an awesome floorplan, even nicer with the added rumpus room and guest with ensuite. makes it complete.
As per our Site Supervisor, we should be in by…
Building Emperor 48
Hi Everyone,
I thought i share some photos of the progress. construction is flying through,
- Pre slab pour inspection was conducted on the 13th of June (Darbecca only picked up four…
Building Emperor 48
Slab down - will post a photo of the frames too.
The Blue cable hanging is for a wireless access point
posted by JPSEmperor48