I have questioned the same thing to Vicky sue.. she is not answered.According to contract, we are not allowed to access the land..but the public can access....I have never seen…
Provincial Homes
Hi
Just updating our work. Slab poured on 5th july .still no fence around my land..next door builder driving their truck just back of my slab and all workers having their…
Provincial Homes
due to heavy rain our land soil is still soggy cant put slab yet..they are not concerned about weeks, asking me to be patience
Provincial Homes
really disappointed.. when they completed piering rain started.. and they have to start slab work by yday ..nothing happening... i have contacted vicky sue and she is advised me…
Provincial Homes
Hi
they have started construction yday.. completed piering yday
Provincial Homes
Final construction plan was signed on 4 th april...before this date they got construction certificate...we are waiting them to start...
Provincial Homes
Since we signed our final contract we never had any rain..but they are saying their works are pending due to rain...I dot understand why its effect my work..dot they have…
Provincial Homes
Hi, thanks for your reply.They have got construction certificate end of March 2017.They came to our land and scraping did on 4th may. they have not put fence and board.i…
Provincial Homes
Hi We are building a new house with provincial homes..we have signed final construction plan by 4th april 2017 and land scrapping done on 4th of may.Since then no work…