Help please... Contract
Hi All
Hope you don't mind me adding my 2 cents to this.
I have never read the MBA contract but I have read plenty of HIA contracts and we use the…
EOT and Rainy Days
Also, all they mention in the contract usually is that the contract period to get the house done, can be extended due to delays like weather. I was given 250…
EOT and Rainy Days
usually there is a total build days (say 250 days) and days for inclement weather (say 20-30 days). Any extensions passed that are supposed to be approved in writing (in…
Elliot Hardie Homes
The reviews are fake - we discovered they are mostly written by their staff or suppliers they deal with. We just built with EHH. The most heartbreaking experience of our…
EOT and Rainy Days
Hmm, i am not sure, very strange that they keep charging just for extending time.
We have had 3 days of extended time, but that didnt come with costs. We were…