Building with Hall & Hart Homes
We had handover of our Elyse 36 with Sienna Contemporary facade in early August & have been in almost a month. Slab was poured in mid December then Framework started…
Building with Hall & Hart Homes
Hi jo-t,
We had our cut out today, the SS said we'll definitely be affected as he cannot book trades at the same time.
Hi Amanda_Ly,
We are looking to build a modified…
Building with Hall & Hart Homes
Hi , our final plans are being sent through today : ) so, we are at exacly the same stage. Like you, i plan to change window size/placement depentant on…
Building with Hall & Hart Homes
We are at Week 11 of our build & brickwork should be completed this week, scaffolding coming on Wednesday for upstairs. We had a delay last week due to…
Building with Hall & Hart Homes
We used Democorp. Didn’t have any issues with them. We had to pay an extra $6k because of asbestos but they took photos and properly documented where the additional asbestos…
Building with Hall & Hart Homes
We had Demolition. Would NOT recommend them. We got surprises with the ceiling insulation and slabs. We were not informed of the possible blow up from 20k to 30k. They…
Building with Hall & Hart Homes
Demo is currently in progress for us and we are using ECO, so far they have been amazingly helpful and upfront about all costs.