Suspend work of non payment of variation
My building rep is an inspector , witness expert and a builder. The services that he is doing for me is helping me with my project and representing me when…
Suspend work of non payment of variation
Around 1k a month for lawyer fees , I have a building rep too that I pay around adhoc when needed.
If not my builder will rip me off
Framing stage non compliant - builder continue work
After I sent a letter from lawyers asking about defects, two days later a engineered from Sydney have provided form 12 aspect for the frames lol
Framing stage non compliant - builder continue work
Yes I can send it to you pm
Framing stage non compliant - builder continue work
The certifer is by the builder and I have my own inspector
Framing stage non compliant - builder continue work
Thanks Simeon,
What if we have frames overhang. He is starting t insulate the whole house and finish cladding this week.
Framing stage non compliant - builder continue work
Hello !!
I am currently building a new double storey home in Qld and I want to know more about non compliant framing stage and in the certifer report it says…
Any good building consultants in Brisbane?
Building representative for new build
Owner supplied items for new build
Thanks Simeon!
My partner is the electrician. We have lights ordered overseas and will take a while to arrive. So we will fit those afterwards
Suspend work of non payment of variation
Thanks Simeon.
The builder has now retracted it, as I added my lawyer to my email. Also work were not stopped at any stage and he didn’t go through the process…
Any good building consultants in Brisbane?
Hi
Are there any building consultants that anyone could reccomend?
Suspend work of non payment of variation
Hi everyone,
Has anyone received a suspension of work due to non payment of variation? And they wanted to back date it for 30 days?
Se
Never notified of the suspension of…
Owner supplied items for new build
Hi All,
We are currently building a new build, we have our own electrician that is doing all electrical. So electrical is not part of the contract. Can we fit off…
HIA Contract Clause 16.2 Delays to Carrying Out the Works Af
Thank you all for the responses. One of the email he sent me was "UNFORSEEN CIRCUMSTANCES" as the title then sends me a variation for daily cost of the delay.…
HIA Contract Clause 16.2 Delays to Carrying Out the Works Af
The builder has not done any work but site cut. I tried to call him to negotiate . What is the definition of commencement? There is an ambiguity around this…
HIA Contract Clause 16.2 Delays to Carrying Out the Works Af
Hello!
Can someone please advise me this Clause 16.2?
My builder is giving me a large variation due to our site having absestos after site cut, We had to organise…
Removing items from contract
Thank you for your reply. Yes maybe the word overthinking was not the right word. I didn’t mean it like that. Sorry if you thought I was rude or anything.…
Removing items from contract
Thanks for your honesty.
I think you are overthinking this. Every build is different, people change their minds all the time. Hence there are variations. You can’t have it perfect first…
Slab design - contract issues
So just a quick update. The builder has now deleted the piering cost. He said it was base on good will. I have asked multiple times if there was something…
Removing items from contract
Hi Everyone,
So we have signed our contract and have paid 5% deposit. The contract includes a swimming pool and prime cost for cabinetry kitchen and laundry.
I’m not a big…
Slab design - contract issues
The trees we have is all in the back of the land and we have cut it all down.
Slab design - contract issues
Yeah the builder didn’t want to go with my design as it was conventional and he wanted to use the waffle design for economical.
Slab design - contract issues
Also I got a conventional slab design done from my engineered and it only had 10 piers.so I don’t know why the builders engineer required 62 piers.