7 years7 yearspEast posted:
Building Arden homes Votivo 37 in South East
Building Arden homes Votivo 37 in South East
Tiling started 12/06/18 and finish on 29/06/18.
Since the house is locked up - view from a window of
Laundry - tiles r 300x600 and shower only tiles r…
7 years7 yearspEast posted:
Building Arden homes Votivo 37 in South East
Building Arden homes Votivo 37 in South East
07/03/2018
Asked SS for DJM certificate frame completion and Engineer’s report regarding frame inspection - both were sent in the afternoon
Hebel on ground floor almost completed
7 years7 yearsManj posted:
Arden Developments
Arden Developments
Yay!! our energy report came in above 6 !! phew!! that was such a relief!! eagerly waiting for contracts next week
7 years7 yearspEast posted:
Building Arden homes Votivo 37 in South East
Building Arden homes Votivo 37 in South East
So have received information that slab is to be poured on 17/11/17 and NHI to do pre-pour slab inspection on 16/11/17
7 years7 yearspEast posted:
Arden Developments
Arden Developments
Hi Dave
How about this landscape idea
Probably a letterbox in a Big rock