Who is building with Allworth Homes
Im about to finish my build, the site supervisor told us that we should have the keys next week (well before the 34 week)
Overall its been a pretty decent experience,…
Who is building with Allworth Homes
So far here is our time lines
Paid Tender in Jan - during this time we made some changes to structure of the house (eg we removed alfresco turned it into…
Who is building with Allworth Homes
For your pir lights, you can just get provisions for the extra areas. Standard lights where about $50 to get wired, down lights are 130 per down light.
Who is building with Allworth Homes
Hey Blake,
Yeah you will have to just wait til your appointment, they basically contract that whole section out to them. You are looking at a couple of grand for…
Who is building with Allworth Homes
Hey Guys,
Your houses look great, we have just lodged our final plans to CDC on Friday.
How as your overall experience been with allworth so far?
Al