Our Arden Home - Votivo 43
Hi Gwij
The first coat of render is a base coat, not your colour, it’s a beige colour. The 2nd coat is the one with your paint colour mixed in,…
Inspired Homes/Como Homes - Handover
Wow, super high ceilings! They will look amazing!
Moving our water tap & meter - South East Water
I enquired about it and you can move it using licensed plumber 600mm without approval but anything more than that you need to apply to SE Water for approval.
Building Arden homes Votivo 37 in South East
Looks great PEast. I think we have the same coloured driveway! Hope you can enjoy your house now.
Arden - Votivo 43
Thanks Mamz,
Yes we loved the windows, so much so that we got the same facade windows added to our living room. They are called Mock Double Hung by A&L,…
Arden - Votivo 43
Thanks Mango C, you have chosen the same? Blackbutt? You won’t be disappointed! Love them.
I’m also on the fb group but my building journey started on the Homeone forum. So…
Arden - Votivo 43
We had a big amount allocated during the quote stage by our request, then site costs were reduced to $23k for P class soil, and screw piles and upgraded slab.…
Arden - Votivo 43
Hi Mango C, no we didn’t look at other options as we wanted it done before handover. Cost $6k. Happy with the work.
Arden - Votivo 43
Hi Mango C, yes they did our driveway. Was just one less thing to worry about.
Arden - Votivo 43
Hi treedance,
Thanks for message. At times it was stressful but we are very happy to be at the end of the process.
Floors are blackbutt, Tempo range, category 10. They…
Arden - Votivo 43
At last we are almost at handover.
What a journey, happy to be at the finish line.
Scrubbed up alright in the end
Arden Homes - Votivo 43 - New home build
How big is your block? Looks a decent size.
Arden - Votivo 43
Exactly a year from site scrape we are at PCI stage.
Any tips, advice, lists you can suggest? Thanks
Building Arden homes Votivo 37 in South East
Hey PEast, Great news. Can I ask at what stage did you get your independent inspector around? At or prior to PCI?
Good luck for handover! Glad u got your…
Building Arden Homes Genoa Verve 26 in North East VIC
Hi there. Keen to know how long from QA, to PCI to handover. We are due to have QA next week
Arden Developments
Hi MangoC, it was listed separately to site costs under OHS but we didn’t have the tiger tails cost, we did sign a long time ago and I know of…
Arden Developments
We also had the $5k crane cost. They have used a crane multiple times, I tried to query it but told it was required. We do have overhead powerlines in…
Arden - Votivo 43
Yes we have an exhaust in downstairs WC/Shower but it’s above the shower
Building Arden Homes Genoa Verve 26 in North East VIC
Good luck! So close.
Does the bank really come and view the property?