Hi Peter,
Coral will not do the tiling of the sides because it becomes a problem to them when the tiles get kicked out of place and they have to fix…
Coral Homes general build thread
Depending on how high the retaining wall is. There are building codes regarding how close to a retaining wall you can place a structure. Google it.
Coral Homes general build thread
Clearances are dictated by Council and/or the Estate you are building in.
Manhattan 21 heavily modified - Coral Homes
This was my build ... viewtopic.php?f=31&t=84545
Manhattan 21 heavily modified - Coral Homes
Yes they will ... With the steel frames up ... Now is the time to go and mark where you want the noggins ... bring a sharpie ...
Manhattan 21 heavily modified - Coral Homes
Hi MrsAJ,
When they install the windows make sure they do not remove the protective film/plastic on the glass and frames. When they start doing brickwork and eventually interior painting,…
Manhattan 21 heavily modified - Coral Homes
Hi MrsAJ,
We both have Manhattan 21's which are heavily modified.
Cheers ...
Coral Homes general build thread
Hi TiredHalo,
Don't let the issues you read affect you. What you should ask with those that had issue is that are they happy with the end results. You…
Coral Homes general build thread
Yes you will. Mine took 96 days from start to finish. This includes weekends where not much work was done.
Coral Homes general build thread
Just get batten lights through clipsal then have a chat with the electrician on site and talk to them about their charges installing your own downlights.
Coral Homes - Manhattan Project (96 Days Build)
Hi StepLee,
I paid $1200.00 for a fully installed Hills Reliance 8 system with 5 sensors and the ability to set and monitor the system on a smartphone.
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Go Manhattans !!! ...
Mahattan Project: viewtopic.php?f=31&t=84545
Coral Homes - Manhattan Project (96 Days Build)
Hi Vonsta76,
I went the Bunnings way with my epoxy floor. It cost me $186.00 for the coloured coat, another $186.00 for the clear coat and $200.00 for tools and misc…
Manhattan 23 - Coral Homes (Week 18: Flooring, Carpet....)
Hi StephLee,
My heavily modified Manhattan 21 which is almost the size of a Manhattan 23 took 96 days to build. You'll be in your new home in no time.…
Coral Homes - Manhattan Project (96 Days Build)
Hi Charlibear,
House is slowly looking more like a home now. Did Crimsafe/3M on all windows and doors, that was an expensive investment but worth it. I am doing…
Coral Homes - Manhattan Project (96 Days Build)
Hello Ryalls,
Yes 96 days. Unfortunately I have 2 months lease to worry about. On the other hand I do not have to rush moving our things, we can…
Coral Homes - Manhattan Project (96 Days Build)
Hi Charlibear,
Including weekends. Started 19/08/2016, Completed 22/11/2016.
Coral Homes - Manhattan Project (96 Days Build)
November 22, 2016
November 22, 2016
Coral Homes - Manhattan Project (96 Days Build)
Thanks H Family Build. I am confident that your dream home will be as wonderful ...
Coral Homes Marcoola 30 Brisbane West
Welcome H Family Build ... Looking forward to see your dreams come true ...
viewtopic.php?f=31&t=84545