3 months3 monthsAshington Homes posted:
KDR "building site" - chances of asbestos & getting rid of bulk concrete
KDR "building site" - chances of asbestos & getting rid of bulk concrete
El Forgo
You seem to be across everything!
I would be surprised if you had asbestos and even if you did have some, it would be very minor as you suggested and…
4 months4 monthsAshington Homes posted:
Costs involved - partially steep site, partially-stilt home construction
Costs involved - partially steep site, partially-stilt home construction
Hi El Forgo
From what you are describing, I would be budgeting at least $6,000-7,000/sqm at an absolute minimum, possibly even $8,000.
This factors in:
1. The sheer amount of steel you…