Meridian 30 Brighton Homes
Best advice is to join the facebook page for Building with Brighton homes. There is so much information on there re bricks/inclusions and photos. As weve been in…
Meridian 30 Brighton Homes
How did you find Brighton Homes? How were your bricks? I have some people say the bricks looked NOTHING like what they chose. I tried to get into the display…
Meridian 30 Brighton Homes
Week starting 9/4/19. Another slow week. Painters worked a couple of days and Electrician has been to remove some tiles in kitchen where kitchen back splash was tiled…
Meridian 30 Brighton Homes
Week starting 2/4/19. Slow week. Monday 2/4/19 kitchen tiles grouted. Painters started Friday 5/4/19. No pics at as lockup stage.
Meridian 30 Brighton Homes
Week starting 25/3/19. Slow week. Tiler started splash back in kitchen on the Monday then has not returned all week. Still tiling and grouting to be done…
Meridian 30 Brighton Homes
Week starting 18/3/19 Kitchen, vanities, laundry cupboards delivered and installed. Lots of bits (panels, doors, knobs etc) missing from kitchen. Tiling started.
Meridian 30 Brighton Homes
Monday 11/3/19 the fit out inside started. Internal doors on, architraves partly done still waiting on skirting and more architraves to do. One guy doing this so taking…
Meridian 30 Brighton Homes
Week just gone. Cornices done, waterproofing in wet areas and external bricks washed.
Meridian 30 Brighton Homes
Week 18/2/19 Brick work done. Bricks Austral grecian gold with off white mortar. They look nothing like what we chose but luckily we really like them. Our roof…
Meridian 30 Brighton Homes
Week 11/2/19. Wall wrap and rough in for electrical and plumbing done and aircon in.
Meridian 30 Brighton Homes
Was surprised to see work being done on a weekend. Windows and external doors in and scaffolding done ready for roof.
Meridian 30 Brighton Homes
Yes looking forward to seeing that. At what stage did you actually get some sort of bin on site? The other build sites in our street are so…
Meridian 30 Brighton Homes
Over the last week the frame has been completed. Looking forward to seeing the roof on.
Week starting 11/2/19. Wall wrap and plumbing and electrical rough in done.