Lakeland Pakenham
Ok we were supposed get titled in feb16 and got delayed till july16
Lakeland Pakenham
Haha still i am yes i can confirm bcoz i saw the nbn device installed. We not moved in yet.…
Lakeland Pakenham
Thank u linda for the reply, and to chris yes its ftth from nbn.
Carlisle Matisse 33
Sorry for the late reply, we end building lexington lux q2 from henley.
Carlisle Matisse 33
Hi Ron, we went with matisse 33 we loved the layout and the extra toilet was a + then we saw the matisse retreat and we liked the master bed…
Lakeland Pakenham
Hi Linda,
Did you move in? how was the internet connection?
cheers
Henley homes, Some General floor plan questions
Hi Fully
For your question yes you can change things like you mentioned above. not sure moving the master bedroom to the back, but some plans have this in the back.
I…
Henley Homes
From 1st July Henley changed to AGL for gas and electricity from Origin.
HIA building contract
Mine volume builder and its 260days and 250wk any delays mind u they don't count holidays.
Henley Homes
Some of the item costs that sales person and admin lady added like - moving hot water system, some external taps movement, prices went up a bit. I have swapped…
Henley Homes
To Khubvalo123
Yes I'm in the same boat as you regarding the product reviews. I think Carlisle Homes have the best reviews I think they used to give iPads for reviews…
Henley Homes
To L0renz0
Most of the time the calculations don for the tender is correct unless you have strong negotiating skills with the tender presenter you can't change the costs. From my…
Fencing - Victoria
Its also depend on the fencing company too. Some willing to chase it up with ur neighbor if you provide the details and also they will wait till both parties…
Sahara Q1 - happy ever after
what are doing with all of that cat 6 cables ?
Re: Henley Carmelle Lux Q2 - Post handover jobs continue
why your developer refusing to pay the rebate? I have one too for fencing hope they will pay the rebate.
good luck mate hope you get the keys as planned
Sahara Q1 - happy ever after
henley says they use intergrain for rich chocolate. I believe same brand for other stains too
Lakeland Pakenham
Thanks Linda
I have chased up further and AYCA-1UE3AC this is the NBN doc that mention about stage 2 but main document says planing to finish in 27 May 16 so…
Lakeland Pakenham
Thanks Linda, not sure when they gonna finish other stages. NBN website says about something about 30th june or something.
Tradies next door using my water meter
Same for me, our back neighbor's builder henley used our electricity and sheltered in my alfresco when raining. I was at work my mum was living at the time she…
Re: Henley Carmelle Lux Q2 - Post handover jobs continue
Hi Snyde
You must be busy and enjoying the house. Hope progressing well in flooring and other things.
good luck mate
Cheers
Re: Henley Carmelle Lux Q2 - Post handover jobs continue
Hei
Your house looking nice, Its getting close
cheers
organising fencing in a new estate
Hi
Theirs a form at the council website you fill that in and email or fax to relevant council. Then they send u the details mostly the address of the…
Re: Henley Carmelle Lux Q2 - Post handover jobs continue
great to see everything moving along.
Dont keep us waiting mate upload the pics
Re: Henley Carmelle Lux Q2 - Post handover jobs continue
Haha you maybe make him an alcoholic with all those slabs you gave not returning to work anymore.
Hopefully the new guy is good.
Building Monaco Lux Q1 - Handover 2 Sep !!!
Looks really nice can't wait to see the finish landscape.