Building with Inspired Homes/Como/Evolveliving/Oakliving?
I am still stuck between lockup and fixing stage. I really envy you because you are almost done.
Surely they should able to close those pending within 2 weeks if…
Building with Inspired Homes/Como/Evolveliving/Oakliving?
You are way too lucky, when did they start yours?
Building with Inspired Homes/Como/Evolveliving/Oakliving?
Guys any progress made in your build?
Building with Inspired Homes/Como/Evolveliving/Oakliving?
Same boat here, they are so slow in getting anything done. Hardly is anything well planned, the sense of urgency or organisation is non existent.
Como Homes, Inspired homes and Oak Living
Too bad some of us got caught in that trap.
Como Homes, Inspired homes and Oak Living
Hi There,
I was wondering if you can share the build cost per sqm for Como Homes. I have someone who is really interest in going custom route.
Building with Inspired Homes/Como/Evolveliving/Oakliving?
Geez, what about if it is gas leak or plumbing issue???
Building with Inspired Homes/Como/Evolveliving/Oakliving?
When a builders takes more than 12 months ++++, where do you draw the line between poor project management skills and issues beyond builder control.
Como Homes, Inspired homes and Oak Living
Avoid Inspired Homes and Evolve living, if you can..the stress and heartaches are not worth it all.
Building with Inspired Homes/Como/Evolveliving/Oakliving?
Hi everyone, how is everyone build progressing?We are at 14 months into our build and still got a long long way to go..!! Always excuses, nothing is their fault.…
Como Homes, Inspired homes and Oak Living
Gladly they are not working together, i know of 2 people who have built through Como Homes....they are happy with end product..
Avoid Inspired Homes if you can they are marketing/sales…
Building with Inspired Homes/Como/Evolveliving/Oakliving?
Anyone so far has finished their build? Happy with the progress or outcome?
Build Period for Double Storey
Sound like you are very lucky, my builder keeps peddling wrong information on delivery dates for different stages and no far nothing goes as per plan with no little or…
Build Period for Double Storey
Is legal for a builder to claim 28 days build delay for 14 days lock down?
Build Period for Double Storey
I would think so too, the builder i have slowest builder in Australia i think so. Taking over 5 months post frame to complete lockup!
Building house in Minta Berwick 2021 - any recommendations f
Whom did you eventually end up with?
Initial Deposit Dispute
Building journey can be very emotional at times. From what i have learnt so far nothing goes according to plan. Better take the $1000 and negotiate the discounts in build…
Opinion on natural light : North front facing house
Looks like the Living/Kitchen area will be facing east? and Bedrooms West? If that is correct, may not be so bad. Do you have another house bordering the bedrooms? Sun…
Build Period for Double Storey
That's what i thought so, looks like my builder will takes more 12 months for a similar project build. It is mentally exhausting, watching others finish ahead of you while…
Building with Inspired Homes/Como/Evolveliving/Oakliving?
The new picks items can still be added to the list, right?
I wonder why is it so hard for them to line up their ducks!!
Building with Inspired Homes/Como/Evolveliving/Oakliving?
Anyone here happy with their build progress or completed build so far?
Building with Inspired Homes/Como/Evolveliving/Oakliving?
Has Evolve fixed all the defects satisfactorily?
Build Period for Double Storey
Is normal to have lockup stage take 5-6 months?
Which ducted aircon size? Daikin 16kW or 18kW?
What did you eventually opt for?