hi guys, has anyone actually installed enduradeck? I am also keen to hear what people have to say
Building with Ausbuild at Harrington Estate, Bridgeman Downs
We settled for land 30th July 2018
Slab pour 5 Oct 2018
Handover was 29 March 2019
See more at: viewtopic.php?f=31&t=92146
Building with Ausbuild at Harrington Estate, Bridgeman Downs
That's not that far! It feels like your house was one of the nicely done ones in stage 2 (at least timewise)!
Today, we were told the tilers have finished and…
Building with Ausbuild at Harrington Estate, Bridgeman Downs
Great, you will be in there soon!
Building with Ausbuild at Harrington Estate, Bridgeman Downs
It feels like such a long wait from lock-up with to completion!
A few houses in the estate seem to be taking forever to get to hand-over after painting, light…
Building with Ausbuild at Harrington Estate, Bridgeman Downs
Looks ready to move in Irish! What's left?
Gas bottle prices - Brisbane. How much do you pay?
Great info, thanks for the research and for sharing
Landscape design - KDR (sekisui house ) Burbank - ST George
Side of the house, from fence to wall is only 1.2m so not much room to work with. I can only place small pot plants hook on wire fence. This…
Building with Ausbuild @ Bridgeman Downs
Now at lock-up stage (as at 20 Dec 2018 )
Building with Ausbuild at Harrington Estate, Bridgeman Downs
We used KSpec too, and I would recommend them.
Building with Ausbuild @ Bridgeman Downs
Hey Valandra
Planned actions between now and Christmas break as below:
“
This week and into next will see the plasterboard – fix, set, sand and cornices. Externally the scaffolding will go up…
Building with Ausbuild @ Bridgeman Downs
Ground level brickwork now in place
Building with Ausbuild at Harrington Estate, Bridgeman Downs
Going really well Irish! And those tiles and cabinetry look fantastic!
Building with Ausbuild at Harrington Estate, Bridgeman Downs
At this pace you might be in there by Christmas 😁!
Building with Ausbuild @ Bridgeman Downs
Now wrapped up and electrical rough-in expected to commence 07th Nov
Ausbuild Finlay 36 - Handover completed!
Congrats Paul, glad to hear nothing major came out of the PCI inspection.
Building with Ausbuild @ Bridgeman Downs
Frame in place and colorbond on site. Happy with progress so far
Building with Ausbuild @ Bridgeman Downs
We drove by earlier today, and they sure have been quite busy, hoping they will keep up the momentum
Building with Ausbuild @ Bridgeman Downs
Hi Jamie
The Newbury is a really nice house plan and the facades are beautiful too!
We are building an Ellison 30s just next door. I was quite pleased they kept going…
Building with Ausbuild at Harrington Estate, Bridgeman Downs
BuLe, please let us know what you find out.
Did you end up finding out about lot 75? I keep forgetting to ask
I have not had a chance to talk to…
Building with Ausbuild @ Bridgeman Downs
I drove past yesterday and i was surprised at how your house and those at the second bend of Needham (lots 25 and 44) are progressing!
We now have our…
Building with Ausbuild @ Bridgeman Downs
Hi Irish, an Ellison 30. How is your build process going?
Building with Ausbuild @ Bridgeman Downs
Site update. I will be uploading progress photos from time to time on the forum. Here goes the first 1
Building with Ausbuild @ Bridgeman Downs
Not the perfect start. On Tuesday i got an email that due to recent rains our slab pour which was schedule for Friday 28th has been rescheduled to Friday…