Hi Jgarcia, did you end up proceeding with Allcastle. I am building with Allcastle but on a vacant block. We are just waiting for our frame to go up. I…
Building the AllCastle Grandworth 42.5+
As an update, nothing has happened since my last update. According to our contract, 'the builder is to commence the building works within 20 working days', anyway the 20 days…
Building the AllCastle Grandworth 42.5+
Hi Shopgirl, how did your move go? Hope you have settled in. The downstairs layout of the Palace Regent 12 is similar to the Grandworth but upstairs is very different.…
Building the AllCastle Grandworth 42.5+
Thank you Shopgirl. I sent an email to AH today to see when we should receive further information about the state date. We are building a modified GW 42.5. We…
Building the AllCastle Grandworth 42.5+
I should have mentioned this, sorry. It's a vacant block of land
Building the AllCastle Grandworth 42.5+
Thank you Shopgirl, this is good to know.
Since the vegetation has to be removed prior to construction. We have killed the vegetation on our block and cut the vegetation as…
Building the AllCastle Grandworth 42.5+
This is my first post. We are building with AH too. We have 4 pegs where each has 3 o/s. What does this mean? We are unsure when 20 days…