Metricon Sentosa 52 Modified
do you have a photo pf the drain in the bath, just want to check they have installed the right one in my house?
it is meant to be chrome
Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Facade coming together
Building a Metricon Hampshire 45 KDR in Melbourne Provincial
some scaffolding down
Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Front facade coming along nicely
Metricon Sentosa 52 Modified
You should have a cabinetry drawing if you met with joinery which has the drawings you would have signed off on
Building with Metricon
i paid per bedroom
not sure yet as still currently being built not up to plastering yet
Metricon Sentosa 52 Modified
Should the bottom of the door frame be metal or wood the rest of the door frame is wood with the base plate aluminium
Building a Metricon Hampshire 45 KDR in Melbourne Provincial
roof tiles just about done
Metricon Sentosa 52 Modified
I much prefer everything being fixed before moving in than having to chase them up after.
Building a Metricon Hampshire 45 KDR in Melbourne Provincial
top started today
Building a Metricon Hampshire 45 KDR in Melbourne Provincial
No only bottom
Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Slab pour a few weeks ago
Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Slab pour tomorrow
Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Drove past today and power is in so should have slab in by late next week
Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Screw piles have gone in
Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Just hit the first snag, during boring of second half of piers the boring failed due to cave in. Now has to go back to engineers
Metricon Sentosa 52 Modified
Do you have your kitchen cabinet drawings? How is it there? Is it squared and to the ground? If not the same they need to pul it out and redo…
Building a Metricon Hampshire 45 KDR in Melbourne Provincial
And Sorrento doors
Building a Metricon Hampshire 45 KDR in Melbourne Provincial
I did upgrade all doors in the the house to Hume lin1
Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Site cut started today. Was told start date was tomorrow. Only found out as neighbour called me
Building with Metricon
I was also wondering about the need for a second hot water unit - was thinking pressure was more of a concern than hot water supply as adding a second…
Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Site start date this Friday - cant see them doing more than a site cut maybe