2 years2 yearsAshington Homes posted:
Building & Developing A Duplex In North Ryde
Building & Developing A Duplex In North Ryde
Hi Budapest
20 mpa was specified by our engineer, but as we have to give a 6 year warranty on structure and 32 mpa is only a little more expensive we…
2 years2 yearsAshington Homes posted:
Building & Developing A Duplex In North Ryde
Building & Developing A Duplex In North Ryde
Hi Everyone
We poured our footings on Friday, went well, 65m3 of 32 mpa concrete. in 70 years time some one is going to have an awful time demolishing them!
Tomorrow…
2 years2 yearsAshington Homes posted:
Building & Developing A Duplex In North Ryde
Building & Developing A Duplex In North Ryde
Hi Everyone,
Things have been a bit slow with all the rain, but we are finally pouring our footings in the morning.
We finished the formwork today and I thought that this…
2 years2 yearsAshington Homes posted:
Building & Developing A Duplex In North Ryde
Building & Developing A Duplex In North Ryde
Quick video showing some demolition footage today.vMCpoxxk4uE