building-expert
Builder refusing to negotiate contract
Governments are corrupted by industry lobbies.
When our corrupt Building Commission was abolished in favour of VBA the first thing they did was to retain most of existing staff, renamed their…
Is this exposed aggregate normal?
A simple procedure may not have prevented the problem but could have put the owner into a better position in relation to the dispute.
1 check and verify contractors qualifications, registration…
Suing builder after failed negotiations at CBS?
Builders obligation is not only to comply with Acts, regulations and standards but also to conform with contractual obligations.
Rusted gutter is not acceptable
Parapet flashing is to short and must…
Would the Water be coming from retaining wall?
The level of soil under your house should be higher than outside. If there is a retaining wall then it must have proper drainage.
Suing builder after failed negotiations at CBS?
Your roof lashings should be accurately cut and fitted, sealed and pop riveted at joints at 40mm centres. Your parapet flashings should be fixed at 500mm centres. Work should be…
Builder refusing to negotiate contract
Great post from Simeon but I would like to add something no one is talking about, power imbalance.
Mostly you will have inexperienced homeowner dealing with educated and experienced builder who…
Building up to Lock up - Owner Builder Permit needed?
I believe you do because you are second builder on the job. If you sell who is going to warrant portion of work you have done? Who is going …
Stormwater capping for demolition
All existing services should be decommissioned and capped prior to demolition or else you risk rubbish in sewer and stormwater pipes, electrical hazard and gas hazard.
No contract until demolition is done on existing dwelling?
The possible trick here is that if the builder is not doing demolition it could be alleged that the demolition is incomplete and has interfered with the classification of site…
What is the pipe in my backyard
Sewer vent, yes you will smell sewer gasses when you sit in your gazebo.
Insurable event claims
Many people have lodged insurance claim for damage to their home from an insurable event only to find the claim either rejected or the insurer offering a settlement well below…
Engineering Drawings for Double Steel Garage?
The supplier does not have proof of "cost" until invoices are paid, ask for a copy of paid invoices
Building inspector recommendations for Melbourne VIC?
Try Nik from Compliance Building Reports
No Occupational Certificate until all landscaping is done
Unfortunately you were badly advised.
If I did your pre contract review I would have flagged potential issue.
Looks like landscaping has to go in asap, all you can do is try…
No Occupational Certificate until all landscaping is done
This should have been no surprise if you had read development approval condition 28.
Why isn't your builder completing all the work, including landscaping?
There would be appeal provisions for the council…
Provisional variations
It does not matter what the content of building contact is because it is Domestic Contract Act 2000 that has the protocol for the administration of PC sums and Provisional…
Provisional variations
Get a good building consultant to review your contract and give you expert opinion
Builder Terminated contract after Variation Requested
If your builder has terminated building contract (rightfully or wrongfully) your contract is at an end. There is no provision for the builder to come back. Financially the builder has…
Help - Insufficient fall for sewerage house connection
Who designed the house?
Questions re: Practical Completion
Your understanding of PC is correct, be firm
Builder Terminated contract after Variation Requested
Read your building contract.
Contract termination is a two step process where firstly a notice of intention to terminate is sent, specifying default and giving time for the default to be…
Help please... Contract
As QS I can tell you that not all rock is excavation in rock.
Many people have paid tens of thousands of dollars for excavations that either are not classified as…
Help please... Contract
It does not matter if you signed the variation if it is not valid or if it is not calculated properly or proven with evidence of cost or if it…
Room not fit for purpose percentage.
More detail would be welcome, why are rooms not fit for the purpose? Even if so then builder should fix the problem under builder's warranty.
Compensation is only paid if the…
Should we build now or wait?
No one answered your question Do you reckon build costs are ever going to drop in future?
No chance, for a number of reasons
1 inflation and loss of currency value
2 increasing…
Is it better to use a bank or a mortgage broker?
The oldest advice in the book, do your homework and shop around.
Help please... Contract
It is a common problem on building sites that builder make errors in levels set out and then try to pass on the cost, or they just try to pass…
At what distance from the house is it safe to plant trees?
It is never a good idea to plant trees close to house foundation however if you must then you can mitigate damage from trees by installing a tree root barrier.
Some…
Active or 'stabilised' slab
Your slab is likely built on highly reactive clay soil and that means that there will be seasonal foundation movement regardless of adequacy of house construction and maintenance.
If the cracking…
Stolen Appliances
Prime suspects are always people on the job. Many times I had lunch with them, shared a joke, paid their wages or contract price, knew name of their kids and…
About
Occupation
Building Expert, Pre Purchase Property Inspection Expert, Expert in Thermal Imaging for Detection of Building Defects, Expert in Building Contract management and Administration, Expert Witness
Interests
Incurable student of almost everything