Yes they did that already after I raise this question about contract saying commencement clause listed out this way and bla bla bl.. later on they came back to…
Building with Kurmond Homes
Thats NOT true at all instance.. they keep changing this sentence!
During our time, when I asked they didnt gave us this option even we took a day off and…
Building with Kurmond Homes
Yes I agree.. they do start asap.. and the construction team is reasonably pushyy.. they are aiming to finish the job asap!
I would say.. Kurmond Admin/Office team are damn slow…
Building with Kurmond Homes
Brick work Done ( took 2 months tp finish - in fact it is 2-3weems job)
Roofing - Done
Gutter fascia - Done
Still plenty things left to reach to the pre-lining…
Building with Kurmond Homes
Thats it.. nothing is in our hand! They made us handicaps...
Building with Kurmond Homes
Does anyone know when KH do outside Cladding?
Our bricks are finished.. !
Building with Kurmond Homes
Kurmond doesn't know the meaning of word "COMMITMENT(S)"...
Building with Kurmond Homes
Same with us...
I am still not getting their strategy/practice to work in this way!
As they being profession - they are handling multiple project and how come they dont know…
Building with Kurmond Homes
Updates: Construction Stage | BRICKS
8 Feb 2018: Bricks arrived on site
15 Feb 2018: Bricklayers started working
3 Mar 2018: Bricklayer has finished 75% of brick works and stopped working because they…
Building with Kurmond Homes
Surprisingly things were going great/on track but as we all know now Kurmond Homes doesn't like to be so good & dont belive in tl provide a great efficient services…
Construction Stage | BRICKS
it is Kurmond Homes Estimating teams problem not brick supplier or bricklayers!
How long did your bricklaying take??
In our case, it took 2 months to finish the brick works of 32 sq double story home.
8 Feb 2018: Bricks arrived on site
15 Feb 2018: Bricklayers started working
3 Mar…
Construction Stage | BRICKS
In our case, it took 2months to finish the brick works.
8 Feb 2018: Bricks arrived on site
15 Feb 2018: Bricklayers started working
3 Mar 2018: Bricklayer has finished 75% of brick…
Building with Kurmond Homes
Updates: Construction Stage | BRICKS
8 Feb 2018: Bricks arrived on site
15 Feb 2018: Bricklayers started working
3 Mar 2018: Bricklayer has finished 75% of brick works and stopped working because they…
Construction Timeline | Lock-up stage
Wow.. My supervisor told me 3 months🙄
Construction Timeline | Lock-up stage
How many months or weeks it took to reach to lock-up stage once brick/roof-tile work has finished?
Building with Kurmond Homes
That's the way! They deserve it...
Hope they can treat you fairly after that call...
Anyone else building in North Kellyville?
Yes, we are building in North Kellyville with Kurmond Homes..
Is anyone else who is building with Kurmond Home? Please share your experience..
Building with Kurmond Homes
SPOT ON - I am 100% agree! We have experienced the same...
Kurmond's office staff can give you false information, misleading commitments, unwanted delays, etc...In short it is easy…
Building with Kurmond Homes
What I have learn from my experience is ----
Mike is a sales person so he will be nice and once you've paid $6000 then that's it - Mike would be…
Building with Kurmond Homes
Nada17
GREAT - CONGRATS for having CC finally
With our Construction Stage - So far so good!
We are at…
Building with Kurmond Homes
Hi I am feeling bit fortunate that I have passed that admin/documentation stage (MOST FRUSTRATING) as we are now in construction stage!
Kurmond's CSO - I will rank them 3/10
*lack of…
Construction stage | FRAMING
thank for the information! helpful..
Our supervisor told us it will take only 2 weeks but it seems it will finish in 3 weeks...
How long was everyone's admin stage?
Paid first deposit in DEC 2016 and our builder started site work in DEC 2017!
It was a FRUSTRATING year!!
Construction stage | FRAMING
Thanks for sharing!! but it is on paper!!!
I would like to know how many weeks generally it takes in real time! As this experience varies from project to project…
Construction stage | FRAMING
Frame Stage Inspection - Please provide a guideline
Construction stage | FRAMING
How long does frame stage take???
Please SHARE your experience!!!!
Building home with Kurmond Homes, South Windsor
So TRUE... SPOT ON!
Kurmond Home is DAMN frustrating!
In our case, they took 11 months for finalising all paperwork/admin process... Finally, they started our construction in last week of x-mas(2017)…